SHEET 038-A · THE BUILD STORY
A rear addition that had to sit beside a 1926 four-square without apologizing for either century. The city asked twice about the roofline; we answered with the drawings, both times, same week. The +2% on the final invoice is the storm drain the county made everyone move that spring — documented, signed, and explained before it was billed.
SPECIFICATIONS
SCOPEGROUND-UP REAR ADDITION
STRUCTURESLAB + LVL FRAME
ENVELOPECEDAR + STANDING SEAM
FINISHPREMIUM
CREW LEADS. VOSS
SCHEDULE — AS BUILTWK 01 → WK 26
26 WEEKS, ONE CREW, A ONE-PAGE UPDATE EVERY FRIDAY
SIGNED ESTIMATE
$286,000
FINAL INVOICE
$291,700
+2.0% VS ESTIMATE
“Every Friday, a one-page update: what happened, what's next, what it costs. Twenty-six Fridays, zero surprises.”
— PRIYA N., GRANT PARK